Redecoration for common areas of a 37 years old building
-Minor refurbishment for an office building which was built in 1971 and refurbished in 1987
-2nd refurbishment completed in October 2008
|
|
Entrance Hall, Before |
Entarance Hall, After |
-Granite floor panels were cleaned and a floor mat was replaced.
-Joint sealing for "Neoparies" was replaced and the surface was cleaned.
-A new recessed ceiling was constructed and indirect & down lightings were installed.
-A mail box was cleaned and post opening caps were installed.
|
|
|
Entrance Hall, Before |
Entarance Hall, After |
-A tenant directory board was replaced.
|
|
|
External Appearance, Before |
External Appearance, After |
-Joint sealing of external "Neoparies" panels at 1st floor was replaced and the surface was cleaned.
-Granite external floor panels were cleaned.
-Surfaces of side signboard were replaced including characters.
|
|
|
Typical Floor Elevator Hall & Corridor, Before |
Typical Floor Elevator Hall & Corridor, After |
-PVC floor tiles and each floor signage were replaced.
-Wall was repainted.
-Ceiling boards were repainted.
-Tenant doors and frames were repainted.
-New down lightings were installed after taking existing lightings out.
|
|
|
Typical Floor Male Toitet, Before |
Typical Floor Male Toitet, After |
-PVC floor sheet was replaced.
-Wall was repainted.
-Ceiling boards were repainted.
-Wash basins and soap boxes were replaced. Washing counter boards were cleaned.
-Lighting bulbs for down lightings were replaced.
-Toilet doors and frames were repainted.
|
|
|
Typical Floor Female Toitet, Before |
Typical Floor Female Toitet, After |
-All existing Japanese type water closets were replaced to western type wash toilets.
|
|
|
Internal Stairs, Before |
Internal Stairs, After |
-PVC floor tiles were replaced.
-Wall was repainted and balustrade copings of artificial stones were cleaned.
-Ceiling was repainted.
-Non-slip rubbers for stairs were replaced.
|